Solar Shutdown Procedure

  • Turn off the AC “Solar Supply Main Switch” located in the Switchboard.
  • Turn off the DC “PV Array Isolator” located next to the inverter.

WARNING: Do not open plug and socket connectors or PV array DC Isolator under load.

  • PV Array Open Circuit Voltage: V
  • PV Array Short Circuit Current: A

System Restart Procedure

We always recommend a restart procedure if an inverter is showing any sign that it is not working properly.

  • Turn off the AC “Solar Supply Main Switch” located in the Switchboard.
  • Turn off the DC “PV Array Isolator” located next to the inverter.
  • You will need to wait 5 minutes and then after that turn the system back on.

It normally takes a few minutes for the system to fully turn on. If there is a fault even after the system restart then we will need to send someone out to check the inverter for you.

If you are in Brisbane then contact us for assistance 07 3286 1422